Locked Events and Tasks

When you are in the process of completing a task or event on a mobile device, a locking mechanism is in place to ensure your completion of the task or event. This means another user cannot open your task or event as long as you are synced to the mobile device and the list shows the item as locked.

If the Event title of a locked item is tapped, the event will open, but will be unavailable for editing.

If the Information icon is selected, edit properties are also unavailable.

Unlock

If you prefer to complete a task on the web rather than on mobile, you can delete the task from your To-Do List.

To delete a task, go to To-Do List > Assigned. Swipe to the left on the task, and then tap the delete icon that is shown to the right.

When you delete a task from the To-Do List, you must be online. If you delete a task when not online, the item is deleted but not unlocked on the web application. In this case, you must resync when connected, and then delete again.

After you delete a task from the To-Do List, it is recommended that you not sync your device until the assigned task's status is changed from Scheduled to Pending in the web application. To update the status, you can start the task on the web or, if you have permission to edit properties, you can bulk update unlocked tasks.

If the task status remains Scheduled the next time you sync, the task is locked and downloaded to your device.